DIRECTORS' REPORT

The Members

The Directors of your Company are pleased to present the Twentieth Annual Report together with the Audited Financial Statements of the Company for the Year ended 31st March, 2015.

1. COMPANY'S PLANTS AND OPERATIONS

At present, your Company has three operative Hydro Power Plants and two operative Thermal Power Plants, namely:

i) 300 MW Jaypee Baspa–II Hydro Power Plant in Himachal Pradesh;

ii) 400 MW Jaypee Vishnuprayag Hydro Power Plant in Uttarakhand;

iii) 1091 MW Jaypee Karcham Wangtoo Hydro Power Plant in Himachal Pradesh;

iv) 500 MW – Phase I (of 1200 MW) Jaypee Bina Thermal Power Plant in Madhya Pradesh; and

v) 1320 MW Jaypee Nigrie Super Thermal Power Plant in Nigrie, Distt. Singrauli, Madhya Pradesh.

Besides the above mentioned power projects, the Company has implemented Jaypee Nigrie Cement Grinding Unit at Nigrie (M.P.) with capacity of 2 MTPA, the commissioning activities of which has started and its commercial operations are expected to commence shortly.

Following the cancellation of coal blocks in terms of judgment dated 25th August, 2014 read with order dated 24th September, 2014 of Hon'ble Supreme Court of India, the Central Government conducted e–auction of coal mines in which your Company participated and was allotted Amelia (North) Coal Mine in Distt. Singrauli, Madhya Pradesh, during the year.

The Plant Availability and Energy Generation of each of the Hydro Power Plants & Thermal Power Plants for the Financial Year 2014–15 were as under:

300 MW Jaypee Baspa–II Hydro Power Plant

The average tariff for Baspa–II Hydro Power Plant for the year under report, as per the Multi Year Tariff (MYT) order dated 15th July, 2011, order dated 6th September, 2012 and in accordance with the Power Purchase Agreement (PPA) works out to Rs.2.77 per unit. The total generation of energy during the year was 1256.96 MUs including 12% free Power to State Electricity Board/Government of Himachal Pradesh and also auxiliary consumption/transformer losses. The Net Saleable Energy during the year was 1100.47 MUs, out of which 1056.92 MUs was Primary Energy and 43.55 MUs was Secondary Energy

400 MW Jaypee Vishnuprayag Hydro Power Plant

The average tariff during the year under report for 400 MW Vishnuprayag Hydro Power Plant works out to Rs. 2.47 per unit. The total generation of energy during the year was 1815.92 MUs (including 22.15 MUs deemed generation). The net saleable energy during the year was 1573.96 MUs out of which Primary Energy was 1545.87 MUs and Secondary Energy was 28.09 MUs. Generation of Power at 400 MW Jaypee Vishnuprayag H.E.P was suspended since 16th June, 2013 due to Force Majeure